The Fröskog hybrid park combines wind and solar power to increase the supply of renewable energy and make more efficient use of the grid connection. Since wind and solar power are often generated at different times, the park can supply energy under varying weather conditions and contribute to a more stable energy supply.
The facility consists of six Vestas V162-6 wind turbines.0/6.2, which began operations in early 2026, as well as a solar farm with a total capacity of 14 MWac, spread across three areas, which is scheduled to begin operations in the spring of 2026. This combination makes it possible to optimize production and reduce the load on the power grid. The hybrid power plant is located in the municipality of Åmål, a few kilometers west of Tösse and the E45 highway. Construction began in 2024.
Related

Åmål

6

14 MWac

2026
Do you have any questions?
Please feel free to contact our site manager
Several projects

Raftsjöhöjden
The Raftsjöhöjden Wind Farm consists of 11 wind turbines with a total capacity of 60.5 MW. It is located in the municipality of Strömsund in Jämtland and began operations in 2022.

Ytterberg
Ytterberg wind farm consists of 22 wind turbines with a total capacity of 44 MW, located south of Malå in Västerbotten and commissioned in 2011.

Åmliden
Åmliden wind farm consists of 29 wind turbines with a total capacity of 52.2 MW, located southeast of Malå in Västerbotten and commissioned in 2012.
Staying in the wind farm
Within the area you can still hike, ski and snowmobile, pick berries and mushrooms, etc. However, in certain weather conditions you need to be alert and pay particular attention to the warning signs. When temperatures approach zero degrees or colder, there is a risk of ice and snow falling from wind turbines and masts. For your safety, you should avoid being near wind turbines and masts due to the risk of falling ice and snow.
There are buried cables and pipes within the wind farm. If you (as a landowner or contractor) are going to dig or carry out work with machinery within the wind farm area, it is important to contact the site manager well in advance to ensure that neither you nor the wind farm’s equipment is damaged.
If you notice a turbine noise or anything else that seems abnormal, please contact us immediately. If you have questions or other concerns, you can also reach us at Vasa Vind via: